case study

Solar Removal and Replacement for Creative City Depot

Raiden Technologies removed, palletised and reinstalled 635 solar panels across two roofs at the City of Sydney’s Creative City Depot. Using a scissor lift instead of a crane, the team made the job safer and simpler while the council’s roof works went ahead.

IMG_7475

Solar panels can be removed for commercial roof replacement without a crane when roof loading is unsafe. At the City of Sydney’s Creative City Depot, Raiden moved 635 panels by scissor lift, stored them on pallets on site, then reinstalled and tested the system.

Project summary

The City of Sydney engaged Raiden to remove and reinstall the existing rooftop solar system at its Creative City Depot ahead of major roof works. Raiden completed a dilapidation report, removed 635 panels across two roofs, and stored them on pallets on site. Once the roofs were complete, the team reinstated and tested the whole system.

Client
City of Sydney
Location
Sydney, NSW
Project date
2026-08-18

The challenge

Roof works across two large roof areas meant 635 existing solar panels had to be removed and later reinstated without damage. There was no safe place on the roof to load a pallet of panels, so the usual crane lift would have created a serious safety risk.

The solution

Raiden designed a scissor-lift method instead, moving panels along a planned path across roof 2. That removed the need for a crane and the risk of loading panels onto a suspended pallet. The panels were palletised and stored safely on site, then reinstated on the existing cabling, inverters and mounting system and tested once the roof works were finished.

Systems Installed

Security and electrical systems delivered on this project.

  • Dilapidation Report

    Condition of the existing panels and system documented before work began.

  • Scissor-lift Access Method

    EWP access along a planned roof path, replacing a crane lift and suspended pallet loads.

  • Panel Removal

    635 panels removed across two roofs (75 on roof 1, 560 on roof 2).

  • Palletised On-site Storage

    Panels loaded onto pallets and stored securely on site during the roof works.

  • Reinstallation

    All panels reinstated on the existing mounting system, cabling and inverters.

  • Testing & Commissioning

    Full system tested to confirm safe, normal operation.

The outcome

The City of Sydney completed its roof works and kept its full existing solar system, with no crane lifts and no new panels, inverters or cabling. The scissor-lift method made the job safer and avoided the cost and disruption of crane hire, and the system was returned to full service.

Outcome metrics

panels removed and reinstated
635
system tested and returned
100%
downtime
0
incidents
0

Project gallery

Architectural Rooftop Solar Array
Blue-Grey Rooftop Solar Installation
Polished rooftop solar above the skyline
Refined Rooftop Solar Array
Refined Rooftop Solar Cityscape
Refined rooftop solar installation

Testimonial

““Raiden came up with a smarter, safer way to handle the solar at our depot. Using a scissor lift instead of a crane removed a real safety risk and kept things simple on site. The panels were carefully stored, reinstated as soon as the roofs were done, and the system was back up and running without any issues.””

Project Manager, City of Sydney

Related capability

Explore connected security, electrical and industry capability across Sydney and NSW.

Frequently asked questions

Can solar panels be removed without a crane?

Yes, if the site allows it. At the City of Sydney’s Creative City Depot, Raiden moved all 635 panels by scissor lift along a planned roof path. That avoided crane hire and the risk of suspended pallet loads.

Why avoid a crane for solar panel removal?

Crane lifts need a safe place on the roof to put down pallets of panels, and lifting suspended loads carries risk. Where the roof can’t safely take the load, a scissor lift or other EWP is often the safer and more efficient option.

How are solar panels stored during roof replacement?

They’re loaded onto pallets and stored securely on site, which protects them from damage and avoids transport. Raiden palletised the Creative City Depot panels and reinstated them once the roof works were complete.

Do you need new solar equipment after a roof replacement?

Usually not. With careful handling, the existing panels, inverters, cabling and mounting can all be reused. The Creative City Depot system was reinstated without any new solar equipment.

How long does it take to remove and reinstall commercial solar?

It depends on the number of panels, how easy the roof is to access and the roofing program. Raiden plans removal and reinstallation around the roofing contractor’s schedule so the solar is back in service as quickly as possible.

Next step

Get a Site Assessment

Tell us about your site requirements, compliance needs and security or electrical scope. Raiden delivers integrated capability under one accountable contract.